QA for product and Patch Releases
Step 1 - Developer to system test changes until not issues are found - Alvis and Sanjay to sign off on System Test
Step 2 - Product expert allocated by Consulting Manager for Product QA.
Consulting Manager to allocate resource
Consulting Manager to sign off on UAT and Generic Test
STEP 1 - DETAILS OF QA can be entered in case comments. Summary to be maintained in the table below.
Test Plan
The following tests were carried out in QA2.
Case | Description | Status |
1 | - Test case in Client database
- Restore Client database (DANAM)
- Upgrade the database and check that the bank details in Menu 329-2 are correct and do not duplicate for any employee.
Database name: CLIENT-DANAM-LINKSOFT | Passed |
2 | - Create a new Demo database in Version 8160.00 Beta 1
- Create a new employee (E069) in Menu 321
- Set Pay Scheme as Direct in Menu 321
- Set employee bank as WBC and ANZ in 326
- Create Standard pay for E069
- Verify that the Bank details are not double in 329-2
Database name: LinkDemo-816 | Passed |
3 | - Amend bank details for E069
- Set Pay Scheme as Cash in Menu 321
- Create Standard pay for E069
- Verify that the Bank details do not appear in 329-2
Database name: LinkDemo-816
| Passed |