Subject: | Incorrect date displayed on the "Applicant Listing" report |
Summary: | Hi Sanjay, Issue: Incorrect date is illustrated on the "Applicant Listing" report. The below was done: - Registered a new user on 18/06/2018.
- Applied for a vacancy on 18/06/2018 at 7.24 am
- Generated the "Applicant Listing" report with date 18/06/2018, no record was populated.
- Generated the report with no dates, the Last Login was at 06/17/2018 9.24PM.
Test Environment - Version 9.4 Beta 6
- Database - LINKSOFT on QA1 - Demo Setup.
- User - Ash and Password - 12
- URL - http://10.0.0.11/RM
|
Audit Notes: | |
19 Jun 2018 | 01:11PM Comment 1 by Alvis (Link Technologies) Case 9348 added to project 09.4 |
19 Jun 2018 | 01:19PM Comment 2 by Sanjay (Link Technologies) Assigned To: Development Followup Date: 19-06-2018 01:19 PM Time Taken: 1.00 |
| Development work for this case has been completed. The change will be available in version: 9.4 beta 7 1. The following changes were made(Include Database object names, Program classes and any other relevant information):| - Applicants created in the system has "date created" stored in UTC date format. We have changed the report to convert UTC date to local date and display local date/time.
2. The issue was caused by: - Applicant's "DateCreated" is stored in UTC date. The report did not convert UTC to local.
3. Next Step - UAT
|
|
21 Jun 2018 | 04:00PM Comment 3 by Sanjay (Link Technologies) Assigned To: Rashna (Edge Business Solutions) Followup Date: 21-06-2018 04:00 PM |
| System test completed. Proceed with UAT on version 947 BETA7. |
|
22 Jun 2018 | 12:41PM Comment 4 by Rashna (Edge Business Solutions) Assigned To: Sanjay (Link Technologies) Followup Date: 25-06-2018 12:00 AM Time Taken: 1.00 |
| Hi Sanjay,
This case has been successfully tested.
Documentation is not required for the case.
Test Environment - Version 9.4 Beta 7
- Database - LINKSOFT on QA1 - Demo
Test Plan - Create an applicant "Allice" and apply for vacancy V1009 on 22/01/018.
- Generate the "Applicant Listing" report with date 22/01/2018, the record should show for the applicant "Alice" - Pass
- Generate the "Applicant Listing" report with no dates, the record should show for the applicant "Alice" - Pass
- Generate the "Applicant Listing" report with date 21/01/2018, the record should not show for the applicant "Alice" - Pass
- Generate the "Applicant Listing" report with date 23/01/2018, the record should not show for the applicant "Alice" - Pass
Thanks Rashna |
|
22 Jun 2018 | 01:06PM Comment 5 by Sanjay (Link Technologies) Assigned To: Sanjay (Link Technologies) Followup Date: 22-06-2018 01:06 PM |
| Thanks Rashna. |
|
09 Oct 2019 | 08:14AM Comment 6 by Sanjay (Link Technologies) Quality control status: Pass. QC Not required - This case was created before quality check was implemented in version 11 on 30/06/2019 |