Subject: | Incorrect Calculation of Cleaner Allowance. |
Summary: | 1. Issue Description (Current behaviour and expected behaviour): Ravinesh advised that the cleaner allowance calculated as per number of hours worked for a day is incorrect. After discussing, the following was highlighted with reference the example below: - Employee 40341 worked 6.67 hours (normal hour) on Monday - Shift hour for Monday is 9 hours
- Employee received Cleaner Allowance of 13.42 whereas Cleaner Allowance figure should have been the same as the Normal hours worked, i.e Cleaner Allowance should be 6.67 instead of 13.42.
2. Environment Details: (Application version and Patch and any other information that will help identify the issue)
V8009 |
Audit Notes: | |
01 Jun 2017 | 06:15AM Comment 1 by Aarti Pooja Gayaneshwar (Link Business Solutions) Assigned To: Alvis (Link Technologies) Followup Date: 02-06-2017 12:00 AM Time Taken: 1.50 |
| Dear Alvis, The GFI Team has stated that the meal allowance calculated is incorrect. This was customized for them, Reference Case: 7528, Subject: CLIENT-GFI_Allowance-LINKSOFT. The environment is setup in QA4, DB: CLIENT-GFI_Allowance-LINKSOFT Kindly take a look. Regards Aarti |
|
01 Jun 2017 | 08:01AM Comment 2 by Alvis (Link Technologies) Case 8578 added to project 8.12 |
01 Jun 2017 | 02:59PM Comment 3 by Sanjay (Link Technologies) Assigned To: Vineet (Link Business Solutions) Followup Date: 01-06-2017 02:59 PM |
| Hi Aarti, Case 7528 does not have this scenario so this cannot be a system issue. These are new requirements and must be treated as new customizations. I have removed the cases from project 8.12. Case assigned to Vineet, as this is a significant change to the way existing rules are applied. Can you review and confirm the changes? regards Alvis |
|
01 Jun 2017 | 03:00PM Comment 4 by Alvis (Link Technologies) Case 8578 removed from project 8.12 |
01 Jun 2017 | 03:08PM Comment 5 by Aarti Pooja Gayaneshwar (Link Business Solutions) Assigned To: Alvis (Link Technologies) Followup Date: 02-06-2017 12:00 AM Time Taken: 0.50 |
| Dear Alvis, Kindly ignore comment 1. This is a part of their standard product and the issue is happening on site. Support case: 6248. Can we schedule a time for tomorrow and take a look. Regards Aarti. |
|
02 Jun 2017 | 11:19AM Comment 6 by Alvis (Link Technologies) Case 8578 added to project 8.12 |
02 Jun 2017 | 11:20AM Comment 7 by Sanjay (Link Technologies) Assigned To: Vineet (Link Business Solutions) Followup Date: 02-06-2017 11:20 AM Time Taken: 3.00 |
| Development work for this case has been completed. The change will be available in version: 8.12 BETA4 Documentation update required(Yes/No. Add change details below): QA required(Yes/No.Include areas that require testing): Yes
The following changes were made(Include Database object names, Program classes and any other relevant information): - Resolved issue with allowance hours computed twice when there was 2 end time for a day.
Documentation details: |
|
02 Jun 2017 | 03:46PM Comment 8 by Vineet (Link Business Solutions) Assigned To: Aarti Pooja Gayaneshwar (Link Business Solutions) Followup Date: 02-06-2017 03:46 PM Time Taken: 1.50 |
| Bula Vinaka Team Further to our diagnosis with Alvis, this issue was being caused due to multiple end time for employees. Example employee 40341 in our setup signed in at 9.45am and had 2 end time, both at 4.55PM. The below was done to test on Beta 4: - Removed all old time
- Re imported this time from TNA Database.
- Submitted these and verified the quantity for the allocated allowance
- This has been resolved with Beta4.
Best Regards Vineet Ram
|
|